How to identify and list Out of Sequence within P6

This article explains how to isolate and review Out of Sequence activities. Oracle’s Primavera P6 Project Management (P6) scheduling software provides users with three different options when scheduling. These are 1.     Retained Logic2.     Progres

When relationships are important (Copying an activity with its predecessors and successors)

There are situations, where you copy a group of activities including their relationships between each other. This is useful for duplicating activities between various sections or levels. Many of the schedulers are familiar with this scenario so I will not go over this one. This copy process is typic

Assigning Multiple Relationships at Once

Most of us know the trick of linking a group of activities with a Finish to Start (FS) relationship. This is done by selecting multiple activities using Ctrl+click (If the activities are in different locations or non uniformly distributed over the schedule) or Shift+click (If they are